A bank performance guarantee is paid on a demand made in its own words and received before it expires. A dispute about the works does not stop it; fraud can.
Your first message costs nothing: within one working day we tell you whether we can help and what it would cost.
klitos@kleanthousplatis.com
A bank performance guarantee is paid on a demand made in its own words and received before it expires. A dispute about the works does not stop it; fraud can.
The contractor’s bank gave the guarantee when the building contract was signed, for a fixed sum and up to a fixed date. Then the works fall behind, the date comes closer and the contractor does not renew it. This guide is for the owner or developer who holds the guarantee: how the bank decides, what the demand must say, what to do when the guarantee will expire before the building is finished, and what you may keep once the bank has paid.
The bank pays on the guarantee, not on the building contract
A performance guarantee is the bank’s own promise, and the bank reads only its text and your demand. It does not ask whether the works are late or defective.
The Supreme Court held in 2008 that a guarantee given to secure payment immediately on demand, regardless of any protest by the bank’s customer, had to be paid once its formal terms were met, whatever the customer said. In July 2026 the Court of Appeal repeated that a bank guarantee is autonomous and independent of the agreement it secures: once the beneficiary meets the terms and conditions set for payment, the bank must pay.
The bank looks at the guarantee and at your demand. It does not look at the building.
Read the guarantee now, not on the last day
What the demand must say, and by when, is written in the guarantee itself. Read it as soon as there is any doubt about completion. Look for:
- who may make the demand, and whether someone in particular must sign it;
- what the demand must state, often that the contractor has not fulfilled its obligations under the contract;
- any document that must go with it, such as a certificate or a confirmation from the architect or engineer;
- the last day, and whether the demand must be received by the bank by then, not merely sent;
- sometimes a first day, before which no demand may be made;
- the branch or address where it must be delivered.
The wording matters. In the July 2026 case a guarantee required the demand to state that the seller had not, by a set date, registered a property in the buyers’ names. The beneficiary wrote before that date had passed, saying the seller would not have registered it by a later date. The Court of Appeal held that the demand did not follow the terms of the guarantee, and the beneficiary’s claim against the bank failed.
When the guarantee will expire before the building is finished
A guarantee that has expired cannot be called, so the demand has to reach the bank while it is still in force. This is the usual squeeze: the works are late, the guarantee runs to the original completion date, and the contractor does not renew it.
Start with the building contract. If it requires the guarantee to stay in force until completion or a later stage, a contractor who lets it lapse is not performing the contract, and that is a fact the owner can state plainly. Then, in order:
- ask the contractor in writing, well before the expiry, to deliver the bank’s extension by a date you name;
- if the guarantee needs a confirmation from the architect or engineer, ask for it in writing at the same time;
- if the extension has not arrived by your date, prepare the demand in the guarantee’s own words;
- deliver it by hand to the bank on a working day before the expiry, and keep the bank’s stamped receipt.
Do not count on the last day. If it falls on a weekend or a bank holiday, plan to deliver on the last working day before it.
Can the contractor stop the bank paying?
Rarely: a dispute about the works is not enough. A Cyprus court stops payment under a bank guarantee only in exceptional cases, chiefly where fraud is clear.
In 2015 the District Court of Nicosia discharged an interim order that a contractor had obtained against a call on its guarantee by the Municipality of Nicosia. The dispute between them included defects and the reading of an agreement they had made, and the court held that a different reading of that agreement could not amount to fraud or bad faith by the Municipality.
The exception is real, though. In 2011 the District Court of Paphos stopped a demand, on an application made without notice, where the beneficiary had demanded payment unannounced and without cause, while assuring the other side that it was preparing the documents to complete the transaction. So the demand must be honest: a demand that states a default which did not happen is the one a court may stop.
An honest demand, in the guarantee’s words and on time, is very hard to stop.
What you may keep once the bank has paid
The money stands as security for what the contractor’s breach has cost you, and the rest goes back.
In a 1999 case an owner called its contractor’s guarantee on the day it expired, with the works unfinished, and collected £25,000. An arbitration later found that the contractor was not responsible for the delay, and that the owner owed it more for additional works. The Supreme Court held that the owner’s right to collect and keep the guarantee was tied directly to loss caused by the contractor’s breach. There had been neither breach nor loss, and keeping the money without evidence of loss would have amounted to approving a penalty. Judgment was entered against the owner for the £25,000, with interest from the day it collected it.
In practice the sum is brought into the final account. Keep the record that justifies it: the delay, the defects, the unfinished or omitted works, and what each of them has cost. How that account is drawn up at the end of the job is in our guide to handover and the final account.
Call the guarantee to protect your position. Keep it only for what the contractor’s breach has cost you.
What this means in practice
The date on the guarantee decides, so put it in the diary today. If your contractor is late, has stopped the works or will not extend the guarantee:
- find the guarantee and the contract clause that requires it, and note the expiry date;
- read what the demand must state, who must sign it and what must go with it;
- ask in writing for the extension, and for any confirmation the guarantee needs, by a date you name;
- prepare the demand in the guarantee’s own words, and deliver it by hand, with a receipt, before the expiry;
- keep a record of every breach and its cost, for the final account.
Send us the guarantee, the building contract and the dates. We check the text, prepare the demand and the letters to the contractor and the architect, and tell you what the money can then be kept for, for a fixed fee agreed in writing before the work starts. If the contractor has walked off the job, see contractor paid and walked away; for interim payments, construction payment certificates and retention; and for the rest of the building contract, our construction practice.
The guarantee protects the owner only until the day it expires. A demand in its own words, delivered in time, keeps that protection.
Questions we are asked
The contractor has not extended the guarantee and it expires this week. Is it too late?
Not if the demand reaches the bank, in the form the guarantee requires, before it expires. Send us the guarantee and the building contract today: the text decides what the demand must say, who signs it and whether anything must go with it.
Do I have to prove to the bank that the contractor is in breach?
Usually not. A guarantee payable on demand is paid on a demand in the form it prescribes. The Supreme Court held in 2008 that once the formal terms of the guarantee were met, the bank had to pay, whatever its customer said. What your demand states must still be true.
The guarantee needs a confirmation from the architect, and the architect has not given it. What now?
A demand without a document the guarantee requires does not follow its terms, and the bank may refuse it. Ask for the confirmation in writing as early as you can, and take advice at once if it is refused, while there is still time before the expiry.
Can the contractor obtain a court order stopping the payment?
Only in exceptional cases. A Cyprus court stops payment under a bank guarantee where fraud is clear, not because the contractor disputes the delay, the defects or the reading of the contract. If the call was wrong, the contractor recovers the money from the owner, in the account between them.
What should my first message say?
The guarantee, the bank and the expiry date; the building contract and its clause on the guarantee; where the works stand and what the contractor has not done; and the dates of any letters asking for an extension.
Sources
- Συνεργατική Πιστωτική Εταιρεία Πέγειας v. CAA Travel Media Ltd (2008) 1 ΑΑΔ 837, Supreme Court, CyLaw
- Τράπεζα Κύπρου Δημόσια Εταιρεία Λτδ v. Alpha Bank Cyprus Ltd, Civil Appeal 166/2020, Court of Appeal, 30 July 2026, CyLaw
- Γεώργιος Χρυσοστόμου & Υιός Λτδ v. Long Life Construction Ltd (1999) 1 ΑΑΔ 1944, Supreme Court, CyLaw
- Miltiades Neophytou Civil Engineering Contractors & Developers Ltd v. Δήμου Λευκωσίας, Action 1419/15, District Court of Nicosia, 19 June 2015, CyLaw
- Pafilia Property Developers Ltd v. Emporiki Bank - Cyprus Ltd and others, Action 3368/11, District Court of Paphos, 22 December 2011, CyLaw

Need advice on your own matter?
Your first message costs nothing: within one working day we tell you whether we can help and what it would cost.
klitos@kleanthousplatis.com
Kleanthous & Platis LLC Registered law company Cyprus Bar Association HE 441973
Further reading
This article is for general information only and does not constitute legal advice. Laws and their application can change, and individual circumstances differ. For advice on your own matter, contact Klitos Platis at klitos@kleanthousplatis.com.
Receive legal updates by email
When Cyprus law changes, hear it from us
One short email when something changes that matters: new legislation, a decision worth knowing, a deadline. Written by the partners, no marketing, unsubscribe with one click.
You are on the list. The next update on Cyprus law will reach your inbox.
That did not go through. Please write to office@kleanthousplatis.com and we will add you.
Your address is used for these updates and nothing else. Privacy notice.