At handover the building contract decides: practical completion starts the defects period and the retention release, and the final certificate can bind both sides.
Your first message costs nothing: within one working day we tell you whether we can help and what it would cost.
klitos@kleanthousplatis.com
Contractors push to hand over before the year closes, and owners are asked to take the keys before the holidays. What follows is set by the building contract more than by any statute: the date in the practical completion certificate starts the defects liability period and the release of retention, and the final certificate, once issued in its proper order, can bind both sides.
Cyprus law adds less than most people expect, and what it adds matters at the end of a job: how a fixed sum for delay is treated, what a defects clause does not take away, and how long each side has to sue. This guide follows the sequence from handover to the final certificate, for the contractor and for the owner, and ends with what to record, what to keep and which dates to diary.
The contract answers most of the questions, so find its clauses first
The answers at the end of a job are in the contract: its clauses on completion, defects, certificates and delay, and the appendix that fills in the numbers. Several recent judgments of the District Courts concern contracts on the same standard form, whose clauses they quote, and they are used below to show how its sequence works. Under that form, the appendix holds the completion date, the length of the defects liability period, the retention percentage and the rate for delay.
Before relying on any date, find:
- the clause on practical completion and the defects liability period;
- the clauses on certificates, retention and the final account;
- the clause that fixes a sum for delay, and the steps it requires;
- the dispute clause, which may send a dispute to the architect, or to arbitration, before any court.
The dispute clause is not a formality. In a judgment of the Nicosia District Court of 24 January 2022 (Action 889/2012), an owner’s counterclaim for defects and delay was held premature, and in any event unproven, because the owner had not first referred the dispute to the architect for a written decision and then to arbitration, as the contract required. On a FIDIC contract the vocabulary and the sequence are different, and which FIDIC book you hold decides them.
Practical completion is the date that starts the clocks
Handover in the contractual sense is practical completion, and the date that counts is the one written in the architect’s certificate. Under the standard form, when in the architect’s opinion the works are practically complete, the architect issues a certificate, and practical completion is treated for all purposes of the contract as having taken place on the day the certificate states. That day can be earlier than the day the certificate is signed.
In a judgment of 9 July 2024 (Action 267/2015), the Nicosia District Court set out what that certificate started under the contract in that case:
- the twelve-month defects liability period in the appendix;
- a certificate releasing half the retention;
- at the end of the defects period, a certificate for the other half;
- a six-month period for the final adjustment of the contract sum.
Whether the works are practically complete is decided on the facts. The court in that case adopted a summary given by the English Court of Appeal: practical completion is easier to recognise than to define; latent defects do not prevent it, and neither do minor defects; but a house is not practically complete merely because it can be lived in, whatever remains to be done. On the evidence, the court did not accept that the house had been handed over for use before it was connected to the electricity grid.
The defects period: the contractor comes back, and the owner has to call
During the defects liability period, often called the maintenance period, the contractor has both the duty and the right to return and put defects right at its own cost, and the owner has to give it that chance. The Limassol District Court explained the bargain on 6 July 2026 (Action 2027/2020), under a one-year clause in the agreement for the sale of a house its seller had built. The seller undertook to repair, at its own cost and without delay, the defects that appeared within the period. The buyers undertook to tell it, and to let it repair, before bringing in anyone else.
An owner who skips that step does not lose the claim, but may recover only what the repair would have cost the contractor. What must appear within the period is the defect, as a symptom; its cause can be established later. In that case the seller had answered the complaints, year after year, with half measures, so the buyers recovered the whole cost of the repairs carried out by another contractor.
Under the standard form the architect does the calling. The architect lists the defects that appear within the period and may instruct their repair, but no instruction may be issued more than 14 days after the period ends; once the repairs are done, the architect certifies that the defects have been made good. In the judgment of 29 January 2026 (Action 6179/15), the owner’s claim under that clause failed: the letter listing the defects was found not to have been sent to the contractor, and the architect’s instructions came more than a year after the 14 days.
A defect seen during the period should reach the contractor in writing, through the architect where the contract says so, before the period ends.
After the period, the claim survives but has to be proved
The end of the defects period does not end the contractor’s liability for defective work. In the July 2026 judgment the Limassol court held that the one-year clause was not an exclusion clause: it gave the builder the chance to repair at lower cost, without taking away the buyers’ right to damages for defects caused by breach of the agreement or by negligence that appeared after the year. After the period, the owner can still claim, on proof of a breach of the contract or of negligence.
The same court held that, in an agreement to buy a house while it is being built, it is an implied term that the house will be fit for habitation, which it treated as not materially different from a term that it would be built with proper materials and in a proper and workmanlike manner.
Proof is the hard part. The Supreme Court held in Charalambous v. Decostone Ltd (2010) 1 A.A.D. 747 that finding problems or shortcomings in a piece of work does not by itself establish defective workmanship, and does not lessen the duty of the party alleging liability to prove negligence, or a term of the contract and its breach. An independent expert who records the defect, its cause and the cost of repair is what that proof usually needs; our article on building defects and the remedies for them sets out how such a claim is built.
Retention and the final certificate follow the contract’s order
Retention is released, and the final certificate issued, in the order the contract sets, and a certificate issued out of that order may bind nobody. What to review in certificates, retention and the final account is set out separately; three judgments on the same standard form show what the order means at the end of a job.
The January 2022 judgment shows the contractor’s side of the order. A payment certificate stated that €5,000 of retention would be payable when the twelve-month period ended, but the architect never issued the certificate of making good defects or the final certificate. The contractor’s claim for the retention was dismissed as premature.
The July 2024 judgment shows a certificate issued out of order. The architect issued a final certificate without first certifying practical completion, and released the whole retention at once, contrary to the contract. The court held the certificate invalid, so it did not bind the owners, and a part payment made against it did not ratify it. The contractor then had to prove its account by other evidence, and recovered the €24,960.83 that the owners’ own expert accepted, against €77,057 claimed.
The January 2026 judgment shows a certificate that bound. Under that form, unless dispute proceedings begin before the final certificate or within 14 days of its issue, it is conclusive evidence that, where the contract leaves materials and workmanship to the architect’s reasonable satisfaction, they meet it. The exceptions include fraud, a defect that reasonable inspection could not have revealed, and errors of calculation. The architect had issued the final certificate on the day of the practical completion certificate, and accepted that the defects could have been seen then. The owner’s defects claim failed, and the contractor recovered the €4,500 retention with interest from the end of the defects period.
The final account sits inside the same sequence. Under the form in the July 2024 judgment, the final adjustment of the contract sum was to be completed within six months of practical completion: the contractor submits its own assessment within the first half of that period, and the architect confirms the adjustment before the period ends and before the final certificate. The final certificate is due as soon as possible, and at the latest three months after the end of the defects period, the completion of the repairs or the receipt of the contractor’s documents, whichever is later.
A final certificate issued out of order may bind no one. One issued in order and left unchallenged may bind both sides.
Delay at the end of the job
A daily or monthly sum for delay is a ceiling, and recovering it takes the contract’s steps and evidence of loss. Section 74(1) of the Contract Law, Cap. 149, provides that where a contract names a sum to be paid on breach, the other party may recover reasonable compensation not exceeding that sum, even if actual loss is not proved. The Supreme Court has read that with care: in Metallika Iraklis Michailides Ltd v. G & C Exhaust Systems Ltd (2001) 1 A.A.D. 500 it held that more than symbolic or nominal damages are awarded only where the loss is proved, whether or not the parties fixed it in advance.
The District Courts apply that at handover. In the July 2024 judgment the contract fixed €800 a month for late delivery; the owners gave no evidence of their loss and received €50 in nominal damages. In the January 2026 judgment the form also required two steps: the architect’s written certificate that the works ought reasonably to have been completed, and the owner’s written demand, made no later than the final certificate. Neither was taken, no loss was proved, and the delay claim failed.
Taking the building late has its own rule. Where time was of the essence, an owner who accepts performance at a later time cannot claim compensation for the delay unless, when accepting, the owner gives the contractor notice of the intention to claim it (section 55(3) of Cap. 149). Where time was not of the essence, the contract stands and the owner keeps the right to compensation for loss caused by the delay (section 55(2)). So an owner taking over late should reserve the delay claim in writing at handover, whichever applies.
For the contractor, the same clauses are the answer to a delay deduction: the certificate the contract requires, the demand made in time, and proof of the loss. An extension of time is claimed under its own clause, and how delay claims are approached is set out separately.
How long each side has to sue
A contractor chasing its final account may have three years, not six, and an owner is safer planning on three as well. Under the Limitation of Actionable Rights Law of 2012, Law 66(I)/2012, an action on a contract cannot be brought after six years from the day the cause of action is complete (section 7(1)). Section 7(2) shortens that to three years for an action on a contract for the agreed or reasonable fee of a contractor, an architect or a civil engineer, among others.
The Larnaca District Court applied the three years on 28 May 2026 (Action 1593/2018) to a contractor’s claim for the balance due for works under its agreement. On an interim application in 2020 (Action 8044/2014), the Nicosia District Court applied the same three years to owners’ claim against their builder for defects, although on its facts the six years had also run. Until a higher court settles the point, the safer date for an owner to diary is the earlier one.
Time runs from the day the cause of action is complete (section 3), and which day that is depends on the claim and the contract, so it is worth fixing early. The limitation periods in Cyprus are set out in full separately.
What to record at handover
The record made on the day of handover is the evidence both sides will need later, and it costs little to make. Record:
- the date of the inspection, who attended for each side, and who signed;
- every item still outstanding or defective, in a list signed and attached to the certificate;
- the practical completion certificate, with the date it states;
- dated photographs and video of the finished work, before anyone moves in;
- for an owner taking over late, a written reservation of the claim for delay;
- for a contractor, its written request for the certificate, and the date it sent its final account.
The January 2022 judgment shows a list of this kind at work: the architect’s certificate of practical completion carried an annex of every item still to be done or corrected on the day.
The documents to keep and the dates to diary
Keep the documents together, because each later step relies on one of them:
- the signed contract with its appendix, drawings and specification;
- every interim certificate, the practical completion certificate, the certificate of making good defects and the final certificate;
- the final account, with the measurements and instructions behind it;
- every defects notice, each reply and the record of each repair;
- the correspondence on delay and on any extension of time.
Diary these dates as soon as the certificate is issued:
- the end of the defects liability period, counted from the date in the certificate;
- the last day for defects instructions, where the contract sets one; under the form in these judgments, 14 days after the period ends;
- the release of each part of the retention;
- the latest date for the final certificate and, once it is issued, the last day to start the dispute procedure, which under the same form is 14 days;
- the limitation date for your own claim, for which three years is the safer date, for a contractor’s claim for its price and for an owner’s claim on the contract alike.
What this means in practice
At the end of a building job, the certificates and the dates written in them decide who can claim what. For a contractor, that means asking for each certificate when it falls due, keeping the measurements behind the final account, and suing for the retention or the balance well inside three years. For an owner, it means a signed list on the day, defects notified in writing within the period, a written reservation of any delay claim, and a decision on the final certificate before the contract’s time to dispute it runs out.
Where a dispute has already begun, our page on construction disputes sets out how each kind of claim is approached. To start, send us:
- the building contract with its appendix, or the sale agreement if the builder also sold you the property;
- the practical completion certificate, and the certificate of making good defects and the final certificate if they have been issued;
- the final account and the last payment certificate;
- the list of outstanding items and the defects correspondence, with their dates;
- a short note of what is still owed or still defective, and any date that is close.
At handover the date in the certificate starts every clock. The final certificate, issued in order and left unchallenged, can stop them.
Questions we are asked
When does the defects liability period start?
On the date the contract fixes. Under the standard form considered in several recent Cyprus judgments, that is the date of practical completion stated in the architect’s certificate, which can be earlier than the day the certificate is signed. The length of the period is set in the contract’s appendix; in the contracts in those judgments it was twelve months.
Can I claim for a defect after the defects period has ended?
Yes, if you can prove it. The Limassol District Court held in July 2026 that a defects period clause is not an exclusion clause: after the period, the owner can still claim damages for defects caused by breach of the contract or by negligence. The Supreme Court has held that showing problems in the work is not enough; the owner must prove negligence, or a term of the contract and its breach.
When does the contractor get the retention back?
When the release events in the contract have happened and the certificates it requires have been issued. Under the form considered in a 2024 judgment, half was certified at practical completion and the other half at the end of the defects period. In a 2022 judgment a contractor’s claim for retention was dismissed as premature, because the architect had never issued the certificate of making good defects or the final certificate.
Can the owner deduct the agreed rate for late completion?
Only by following the contract’s steps, and the rate is a ceiling. Under section 74(1) of Cap. 149 a sum named for breach caps reasonable compensation, and the Supreme Court has held that more than nominal damages are awarded only where the loss is proved. Under the standard form in a 2026 judgment, the owner also needed the architect’s written certificate of delay and a written demand made before the final certificate.
How long does a contractor have to sue for its final account?
Section 7(2) of Law 66(I)/2012 allows three years for an action on a contract for a contractor’s agreed or reasonable fee, counted from the day the cause of action is complete, against six years for contract claims generally under section 7(1). The Larnaca District Court applied the three years to a contractor’s claim for the balance due for works in May 2026.
Sources
- Nicosia District Court, Action 6179/15, judgment of 29 January 2026 (final certificate, retention, delay under the standard form), CyLaw
- Nicosia District Court, Action 267/2015, judgment of 9 July 2024 (practical completion, final certificate issued out of order, delay sum), CyLaw
- Nicosia District Court, Action 889/2012, judgment of 24 January 2022 (retention not yet payable, defects instructions, dispute clause), CyLaw
- Limassol District Court, Action 2027/2020, judgment of 6 July 2026 (defects period clause, defects after the period), CyLaw
- Charalambous v. Decostone Ltd (2010) 1 A.A.D. 747, Civil Appeal 305/2007, Supreme Court of Cyprus, 1 June 2010, CyLaw
- Metallika Iraklis Michailides Ltd v. G & C Exhaust Systems Ltd (2001) 1 A.A.D. 500, Civil Appeal 10355, Supreme Court of Cyprus, 26 April 2001, CyLaw
- Larnaca District Court, Action 1593/2018, judgment of 28 May 2026 (three-year period for a contractor’s claim), CyLaw
- Nicosia District Court, Action 8044/2014, interim judgment of 7 December 2020 (limitation of an owner’s defects claim), CyLaw
- Contract Law, Cap. 149, consolidated text, sections 55 and 74, CyLaw
- Limitation of Actionable Rights Law of 2012, Law 66(I)/2012, consolidated text, sections 3 and 7, CyLaw

Need advice on your own matter?
Your first message costs nothing: within one working day we tell you whether we can help and what it would cost.
klitos@kleanthousplatis.com
Kleanthous & Platis LLC Registered law company Cyprus Bar Association HE 441973
Further reading
This article is for general information only and does not constitute legal advice. Laws and their application can change, and individual circumstances differ. For advice on your own matter, contact Klitos Platis at klitos@kleanthousplatis.com.
Receive legal updates by email
When Cyprus law changes, hear it from us
One short email when something changes that matters: new legislation, a decision worth knowing, a deadline. Written by the partners, no marketing, unsubscribe with one click.
You are on the list. The next update on Cyprus law will reach your inbox.
That did not go through. Please write to office@kleanthousplatis.com and we will add you.
Your address is used for these updates and nothing else. Privacy notice.